Production planning digitalisation checklist

Production planning digitalisation is a project that moves MRP and capacity planning into software on clean master data and defined processes. This list covers preparation from kickoff to post go-live.

Production, planning and project teams10 min readUpdated November 12, 2026
  • 5checklists
  • 4infographics
  • 3template tables

Production planning digitalisation is a transformation project that moves material requirements planning (MRP), the master production schedule and capacity planning into software, built on correct master data and defined processes. This checklist collects, in order, what needs to be prepared before and during an MRP or production planning project. The ORELSIS delivery team uses the same list as a working reference on projects.

The list is independent of software choice. Whatever system you use, the quality of the plan is capped by the quality of the master data. That is why most items focus on data, process and ownership readiness before the software itself.

Goals and scope

The project should start with a measurable business goal. “Getting off Excel” is not a goal, it is an outcome. The real goals are business results such as better on-time delivery, balanced inventory levels, shorter planning cycles or seeing capacity bottlenecks in advance. Measure today's value for each goal; if you can't measure it, your first task is to define how.

Project flow
  1. 01Goals and scopeBaseline measurement
  2. 02Master dataCleanup and ownership
  3. 03Pilot lineTrial with limited risk
  4. 04CutoverReconciliation and decision
  5. 05MeasurementPost go-live KPIs
Each stage builds on the output of the one before.
Goal and scope checks0/8 done

Keeping scope narrow and going deep is usually better than going wide and staying shallow. Starting phase one with a single site or product family and then scaling a working model carries less risk than bringing the whole factory live at once.

Master data: item master, BOMs and routings

The MRP calculation rests on three core data sets: the item master (what?), the bill of materials (made from what?) and the routing (how and where?). An error in any one of them spreads through the whole plan. Master data work is the longest and most critical work package of the project; manage it with its own owner and schedule.

The three core data sets of MRP
Item master
  • Code and type
  • Unit conversions
  • Lead time
  • Planning parameters
Bill of materials
  • Component quantities
  • Scrap rates
  • Revision and validity
  • Alternative components
Routing
  • Operation sequence
  • Work centre
  • Setup and run time
  • Subcontracted operations

Item master

  • Unique item code and a coding rule (has the smart vs. non-smart code decision been made?).
  • Item type: raw material, semi-finished, finished good, packaging, consumable, spare part.
  • Base unit of measure and alternative units with conversion factors (kg, piece, metre, case).
  • Procurement type: purchased, manufactured or subcontracted.
  • Purchasing and production lead times (in days, with realistic values).
  • Planning parameters: safety stock, lot sizing rule, minimum and multiple quantities.
  • Lot and serial tracking requirements, shelf life and expiry date rules.

Bill of materials (BOM)

  • One valid production BOM for every finished and semi-finished item.
  • Component quantities in the base unit, scrap rates in a separate field.
  • Validity dates and revision number (how will engineering changes be managed?).
  • Alternative components and substitution rules.
  • Phantom (sub-assembly) levels; for process manufacturing, recipes, by-products and co-products.
  • An owner for differences between the engineering BOM and the production BOM.

Routings and operations

  • Operation sequence for every manufactured item and the work centre for each operation.
  • Setup time and per-unit run time kept separate.
  • Queue and move times between operations.
  • Alternative work centres and their priority order.
  • Subcontracted operations and the related supplier link.
Master data readiness checks0/8 done

The most common mistake is moving master data into the new system without cleaning it first. A wrong unit, a missing scrap rate or an outdated BOM revision produces wrong requirements in the new system too; this time users blame the software and trust in the system is lost.

Capacity and work centre model

The capacity model shows whether the plan is physically feasible. A work centre can be a machine, a line, a cell or a team. The right level of detail depends on the level at which you make planning decisions: if you don't plan each machine separately, making each machine its own work centre adds needless complexity.

  • Work centre hierarchy: site, department, line, machine.
  • Shift calendar, public holidays and planned maintenance stops.
  • Available capacity: shift length, number of parallel machines and efficiency factor.
  • A list of bottleneck work centres and whether they need finite capacity planning.
  • Whether machine and labour capacity are planned separately or together.
  • Whether secondary resources such as moulds and fixtures are capacity constraints.

A practical approach: first calculate material requirements correctly with infinite capacity, then move to finite capacity scheduling only at bottleneck work centres. OREL MRP shows capacity load per work centre, so you see which line is overloaded in which week before the plan is released.

Inventory and warehouse data

MRP calculates net requirements by subtracting on-hand stock and open orders from gross demand. If stock is wrong, net requirements are wrong. That is why stock accuracy should be confirmed by a physical count before go-live, at least for critical materials.

Inventory and warehouse checks0/8 done

Backflushing reduces the recording workload, but it hides stock differences if BOMs and scrap rates are wrong. If you choose this method, schedule more frequent counts in the first months.

Planning parameters

Planning parameters determine how and in what quantity the system proposes requirements. Parameters are not entered item by item; they are assigned to groups through a classification such as ABC/XYZ and reviewed regularly at group level.

Inputs and outputs of the planning cycle
  1. 01DemandForecast and firm orders
  2. 02Master production scheduleFinished-goods plan
  3. 03MRP runNet requirements
  4. 04Proposed ordersPurchasing and production
  5. 05Shop floor and supplyExecution and feedback
ParameterWhat it determinesWho decides
Master production schedule (MPS)What finished goods to make, and whenPlanning + sales
Planning horizon and frozen zoneHow far the plan reaches and which part is fixedPlanning manager
Safety stockBuffer against demand and supply uncertaintyPlanning + purchasing
Lot sizing ruleLot-for-lot, fixed quantity, periodic, etc.Planning + production
Minimum and multiple quantitySupplier or machine constraintsPurchasing + production
Lead timeHow early an order is releasedPurchasing + production
Forecast consumption ruleHow orders consume the forecastPlanning + sales
  1. 01
    Clarify demand inputs

    Write down which source, how often and with whose approval the sales forecast, firm orders and stock targets will arrive.

  2. 02
    Build the master production schedule

    Balance the weekly or daily finished-goods plan against capacity; set an approval rule for changes inside the frozen zone.

  3. 03
    Run MRP

    Calculate net requirements, create proposed purchase and production orders, and list exception messages (expedite, defer, cancel).

  4. 04
    Manage exceptions

    Planners review only exceptions, not every proposal. If the exception count stays high, it is a parameter or data problem.

  5. 05
    Release and monitor the plan

    Send approved orders to the shop floor and purchasing; review the gap between plan and actuals in a regular meeting.

ERP and accounting integration

A production planning system usually works alongside the ERP and accounting system. At the start of the project, decide which system is the source of truth for each data object: is the item master created in the ERP, are BOMs managed in the planning system, in which system is a stock movement finalised? Changing these decisions later is expensive.

  • Master data flow: in which direction and how often items, business partners, BOMs and routings are transferred.
  • Transaction flow: sales orders, purchase orders, work orders, production receipts and consumption records.
  • Cost flow: how work order costs reach accounting and with which period close.
  • Error handling: who sees failed transfers and who fixes them.
  • Reconciliation: regular comparison of stock and work order status across both systems.

For integration design details, see the “ERP and system integration guide”. OREL DM can be used to collect and match data from different systems on one platform and produce reconciliation reports.

Pilot line, roles and responsibilities

A pilot lets you test the system in real production with limited risk. A good pilot line is representative (it covers the factory's typical products and operations), manageable (the product count is reasonable) and has a willing team. Starting with the most complex line slows learning; the simplest line won't reveal the real problems.

Choosing a pilot line
Data and team readiness →
Easy but teaches littleWon't reveal real problems
Ideal pilotRepresentative and ready
Not suitable for a pilotLeave for later phases
Clean the data firstCandidate once ready
Representativeness →
The line in the top-right quadrant is the best pilot candidate.
Pilot line selection criteria0/6 done
ActivityResponsible (R)Accountable (A)Consulted / informed
Goals and scopeProject managerSponsorDepartment heads
Item master and unitsMaster data ownerPlanning managerPurchasing, warehouse
BOMs and routingsManufacturing engineeringProduction managerQuality, planning
Planning parametersPlanning specialistPlanning managerPurchasing, sales
IntegrationIT / integration teamIT managerAccounting, software team
Data migration and reconciliationMaster data ownerProject managerIT, warehouse
TrainingKey usersProject managerHR, shift supervisors
Go-live decisionProject managerSteering committeeAll departments

Appointing a key user from each department is recommended. The key user tailors the system to their department, runs the tests, trains colleagues and is the first point of support after go-live. If this role doesn't get regular weekly time, the project schedule slips.

Data migration and cutover

Cutover is the move from the old method to the new system within a planned window. Master data can be migrated some time in advance, but open balances (stock, open orders, open work orders) should be taken as close to the cutover moment as possible.

  1. 01
    Prepare migration templates

    Create templates for each data object with the field list, mandatory fields, code mappings and validation rules.

  2. 02
    Run trial migrations

    Run at least two full trial migrations into the test environment; don't move to the live migration until the error list is closed.

  3. 03
    Reconcile

    Compare record counts, stock quantities and open order balances with the source system; close differences with a signed reconciliation record.

  4. 04
    Plan the cutover window

    Track the transaction freeze, final count, open balance migration and first planning run with an hour-by-hour plan.

  5. 05
    Write the fallback plan

    Decide in advance under which conditions, by whose decision and how you will return to the old method if a critical problem occurs.

Don't schedule cutover on top of month-end close, peak season or a major shipping period. Users work more slowly in the first weeks after cutover; stacking that period on a busy operation puts both production and trust in the system at risk.

Training and go-live criteria

Training should use role-based business scenarios, not screen tours. A planner needs the answer to “how do I update the plan when a rush order arrives?” far more than “how do I run MRP?”

  • A role-based training plan: planner, buyer, warehouse, shift supervisor, operator, manager.
  • A training environment and scenarios built on real data.
  • Short, visual work instructions (one page, one task).
  • Hands-on assessment after training.
  • A hypercare plan with on-site support for the first weeks after go-live.
Go-live criteria0/7 done

Post go-live KPIs

Go-live is not the end of the project, it is the start of measurement. Measure post go-live values with the same method as the baselines you set during the goals and scope phase. Review KPIs weekly in the first months and monthly once the process has settled.

KPIDefinitionWhy it matters
On-time deliveryShare of orders or work orders completed on timeKeeping promises to customers
Schedule adherenceMatch between planned and actual productionFeasibility of the plan
Inventory accuracyShare of items where count matches system stockReliability of the MRP calculation
Days of inventoryAverage stock relative to daily consumptionTied-up capital
Exception message countWarnings per planning runData and parameter quality
Bottleneck loadLoad / capacity at bottleneck work centresCapacity management
OEEAvailability × performance × qualityEquipment effectiveness

KPI definitions must be the same for everyone. For example, if you don't write down whether “on time” in on-time delivery means the customer ship date or the warehouse receipt date, departments will read the same number differently. For details on measuring OEE, see the “OEE measurement and improvement guide”.

Conclusion

Production planning digitalisation is less about installing software and more about discipline in data, parameters and ownership. Teams that set measurable goals, clean their master data, learn through a pilot and keep measuring after go-live get lasting results. Reopen this list at every stage of your project and bring unfinished items to the next steering committee agenda.

OS
The ORELSIS teamThis guide is based on the way our team works on projects.